Decorating is the last trade on site and the first one to absorb everybody else's problems. Fill a bad joint and the painter will hide it, or fail to. Fit a door badly and the painter will be blamed for the shadow. It is also the cheapest trade per square metre, which is why it is estimated in a hurry.
That hurry is a mistake, because decorating is the only trade the client sees every day for the rest of the building's life. A paint system that fails at year three costs more in reputation than the whole decorating budget.
This guide covers the measurement, the specification, and the practical allowances that turn a rate per square metre into a number that survives contact with a real building.
The quantity for decorating is the area of every surface to be coated, measured separately because each has a different rate.
A quick check for a room: perimeter x height, less 2 m² per door and 1.5 m² per window, less half the opening area again if you are deducting but still painting the reveals. Many estimators deduct the opening and forget the reveals, which is a small understatement that repeats in every room.
Walls and ceilings are usually painted the same colour in the same system, so on domestic work you can measure the floor area once and derive both:
Wall area is roughly 2.2 to 2.5 times the floor area for a room of normal proportions with a 2.4 m ceiling and one or two openings. Add the ceiling itself at 1.0 times the floor area.
So a 20 m² room is about 44 to 50 m² of walls plus 20 m² of ceiling, roughly 65 to 70 m² of paint surface. That rule breaks down in a room with a high ceiling, a bay or many openings, which is why it is a check and not a method.
A three bedroom house, 95 m² of floor area, walls and ceilings in emulsion, woodwork in satin, plus external masonry to two elevations.
Internal:
External:
That is the quantity. The specification decides the rest.
The system. Two coats of emulsion over a mist coat is the minimum. Three coats, or a primer plus two, is what a colour change or a patchy substrate needs.
The paint quality. A trade vinyl matt and a premium washable matt differ in price by two or three times, and in durability by more. On a rental or a hallway, the difference is worth paying for.
The substrate condition. New plaster absorbs, previously painted surfaces may be silk or contaminated, and distemper or old lime wash will not accept modern paint without removal. Preparation is 40 to 70 percent of decorating labour and it is the part clients want to cut.
The finish. Matt, silk, eggshell, satinwood, gloss, each with different opacity and different rates. Dark colours over light need more coats than the coverage figure suggests.
Filling, sanding, caulking, masking, protecting, dusting. On a refurbishment, half the decorating hours are these tasks, and they cannot be compressed without the finish showing it.
A practical allowance per room, for a standard refurbishment:
On new plaster the preparation is different but not smaller: a mist coat, filling of any pinholes, and sanding between coats.
A litre of emulsion covers 10 to 14 m² per coat on a sealed surface, and less on new or absorbent plaster. Gloss and satin cover 12 to 16 m² per litre.
For 303 m² of emulsion in two coats at 12 m² per litre per coat: 303 x 2 / 12 = 50.5 litres. Tins come in 2.5, 5 and 10 litre sizes, so this is five 10 litre tins or a mix, and there is always a part tin left.
Three buying decisions matter:
For one painter on domestic work:
| Surface | Per day |
| Walls, emulsion, two coats | 40 to 60 m² |
| Ceilings, emulsion, two coats | 30 to 45 m² |
| Woodwork, satin, prepared and two coats | 8 to 15 m² |
| Doors, both faces and edges | 3 to 5 |
| External masonry, two coats | 30 to 45 m² |
| Gloss to metalwork | 15 to 25 m² |