How to Take Off a Kitchen Fit Out

Why kitchen quotes vary by a factor of three

A kitchen is the most quoted room in a house and the least comparable. Two suppliers can price the same plan at figures differing by three times, and both can be honest, because they are not pricing the same thing.

One is pricing cabinets and a worktop. The other is pricing the removal of the old kitchen, the electrical alterations, the plumbing moves, the plaster repairs behind the old units, the flooring, the decorating, the plinths, the panels and the skip. The units are often less than half of the total.

So a kitchen takeoff has to be built in layers, and the layers have to be written down. This guide covers them in the order they are measured.

Measure runs, not floor area

Kitchens are measured in linear metres of run, not in square metres. A 4 m by 3 m room is not a 12 m² kitchen, it is however many metres of cabinet the walls will hold.

Measure the wall length available in each elevation, deduct the gaps for a fridge, a cooker or a doorway, and add the returns. Then split the run into three heights, because they are priced differently:

A 4 m wall that is base and wall gives 4 m of each, which is 8 linear metres of cabinetry. That is the number suppliers quote, and it is worth checking that they count returns and peninsulas in the same way.

The worktop is its own takeoff

Worktop is priced by length, but the length that matters includes the joints and the cutouts.

A stone worktop on an L shaped kitchen can easily consume 4.5 m of slab for 3.8 m of run. That difference is a real cost and it appears on the template drawing, not on the plan.

Cabinets, and what the price per unit hides

Base unit prices vary for reasons that are invisible on a photograph: carcass thickness, drawer runners, hinges, the presence of a service void, and the finish inside.

For a takeoff, count units by type rather than averaging:

Then count the fillers, end panels and plinths. On a typical kitchen these come to 8 to 12 percent of the cabinet cost and they are frequently quoted as an allowance rather than counted.

Appliances and the services behind them

Appliances are typically priced in or excluded, and the decision changes the whole estimate. What matters for the takeoff is not the appliance price but the service each one needs:

|---|---|

ApplianceService required
Electric oven6 mm² dedicated circuit, often 32 A
Induction hobDedicated circuit, 32 to 40 A
Gas hobGas point plus an isolator, and ventilation
Extractor, ductedDuct route to outside, plus a switched supply
Extractor, recirculatingSwitched supply and filters
DishwasherCold supply, waste, switched socket
Washing machineCold and hot supply, waste, socket
Fridge freezerSocket, ideally on its own circuit

The ducted extractor is the item that changes building work: a 150 mm duct to an outside wall is a hole, a route above ceiling level and possibly a fan in the loft. It is a construction cost, not a kitchen cost, and it is the most commonly missed line on the whole job.

Sinks, taps and the things that leak

Moving a sink 400 mm along a wall can mean rerouting a waste with a fall, which is a plumber's job and a hole in the wall. Every kitchen fit includes at least one of these moves.

Electrics: sockets, lighting and the coordination problem

A kitchen fit always includes electrical work, and it is the part most often left out of a supplier's quote:

Count them as points, then add the making good: every new socket above a worktop is a chase and a repair, and a tiled splashback that has to be removed and replaced.

A worked example, L shaped kitchen

A 3.6 m run along one wall and a 2.8 m return, with a 0.6 m gap for a doorway:

That is roughly 45 lines once it is broken open, and any of them can add a day or a hundred pounds to the job.

Where the money actually goes

Break a mid range kitchen down and the proportions surprise most clients. Cabinets and doors are around a third. Worktop is 8 to 15 percent depending on material. Appliances are 15 to 25 percent. The construction work, meaning the electrical, plumbing, plaster, flooring and decorating, is the remaining third and it is the part with the widest spread between quotes.

That is why a client comparing three kitchen quotes should compare the construction scope line by line first. Two quotes with identical cabinets can differ by 40 percent on the plastering and electrical they have quietly included or excluded.

Wall removal and the open plan temptation

A large share of refurbishment kitchens involve taking out a wall. That single decision changes the estimate from a fit out into a building project.

A load bearing wall needs a structural assessment, a beam designed by an engineer, temporary support during the work, and building control approval. A 3 m opening can easily cost more than the kitchen cabinets, and the beam is usually ordered after the engineering, so it sets the programme.

The takeoff consequence is that a kitchen estimate should record whether the layout depends on a removed wall, and if so, that the structural cost sits outside the kitchen figure. Mixing the two produces a number that looks competitive and cannot be delivered.

Ventilation and the rules that catch people

Extraction is a building regulation in most markets, and the rule is about airflow, not about the presence of a fan. A recirculating cooker hood does not meet the requirement in many jurisdictions for an internal kitchen.

Ducting a hood to an outside wall needs a route. The good route is short, straight and slightly downhill to the outside, so condensate drains out rather than back. The bad route is a flexible duct squeezed through a cupboard, which halves the airflow and doubles the noise.

Cost the ducting, the wall terminal, the core drill and the making good as separate items. On a solid brick wall with a stone lintel above, that is not a small job.

Storage, accessories and the 10 percent nobody counts

Individually these are minor. Together they are 8 to 12 percent of the cabinet cost, and they are the items that get cut when a budget is trimmed after the contract is signed, which is exactly when they are most visible.

Sequence and the cost of getting it wrong

The kitchen is installed in a fixed order: strip out, first fix electrics and plumbing, plaster and make good, flooring, units, worktop template, worktop fit, appliances, splashback, sealing, snagging.

Two consequences for the estimate. The worktop template happens after the units are in, so there is a gap of a week or two when the kitchen cannot be used. And the flooring decision matters: laying flooring around units rather than under them saves material and creates a problem when an appliance is replaced.

Allow a realistic programme of two to three weeks with gaps, and write it into the quote. A kitchen quoted as a five day job is a kitchen that will overrun.

Payment, deposits and the risk that sits with the client

Kitchens are usually sold on a deposit, and the deposit is usually large enough to matter. A 50 percent deposit on cabinetry is normal because the units are made to order and cannot be resold.

Two things belong in the estimate as risks rather than costs. Made to order items cannot be cancelled after the order window, so any change after that date is a write off. And installation dates depend on the worktop template, which depends on the units being level and complete, so one damaged cabinet delays the whole room.

A programme with float between unit fit and worktop template is cheaper in stress than one without, and it costs nothing to plan.

Frequently asked questions

How do I compare kitchen quotes? Normalise to the same cabinet specification, the same worktop material, and the same scope of electrical, plumbing and making good. Then compare the exclusions.

How many linear metres is a kitchen? A typical domestic kitchen is 6 to 10 linear metres of base units, with wall units on roughly half of that.

Is the worktop included? Sometimes, often not, and almost never with the joints and cutouts counted. Ask for the template drawing.

Who does the electrical work? An electrician, certified. If the supplier's price excludes it, the number you are comparing is incomplete.

How long does a kitchen take? Two to three weeks for a full replacement, including the worktop gap. Ten days is optimistic for anything with plumbing moves.

Should flooring go under the units? Under the units is better for appliances and future changes, and it costs more material. Around the units is cheaper and creates a trap.

Build the estimate in FRELUX

The FRELUX kitchen takeoff counts units by type, worktop with joints and cutouts, appliances and the services each one needs, then prices the whole fit from your market's price book so the layers stay visible.

Boiling water tapCold supply, socket, and often a filter