How to Estimate Screeds and Floor Finishes

Floors are measured in layers

A floor finish is the smallest part of a floor. Under a tile or a timber board there is usually a screed, sometimes insulation, sometimes a membrane, and always a decision about level and flatness. The layers are measured in different units and they are ordered at different times.

Getting this wrong is expensive in a specific way. A screed that is 10 mm too thin fails, a screed that is too thick adds weight and height, and a floor that is not flat enough makes the finish fail no matter how good the finish is.

This guide takes the layers in order, from the sub floor up, and gives the quantities for each with worked examples.

Flatness is a specification, not a hope

Before any quantity, decide what flatness the finished floor requires. It is expressed as a deviation over a length, for example 3 mm under a 2 m straightedge, and it is written into the specification because different finishes need different tolerances.

The consequence for the estimate is that a floor needing a levelling compound carries a material line for the compound and a labour line for applying it. That is often 10 to 20 percent of the floor cost, and it is invisible on a plan.

Screed: the thickness that decides everything

A screed is a levelling layer, either bonded to the base, unbonded on a membrane, or floating over insulation. The minimum thickness depends on the type and on whether it is reinforced:

|---|---|

Screed typeTypical minimum
Bonded sand and cement25 to 30 mm
Unbonded sand and cement50 mm
Floating over insulation65 to 75 mm
Reinforced floating65 mm with mesh
Flowing screed, calcium sulfate35 to 40 mm

Volume is area x thickness, plus 10 percent for shrinkage and waste. A 60 m² floor at 65 mm floating screed is 60 x 0.065 = 3.9 m³, plus 10 percent = 4.3 m³.

Screed is usually delivered as a readymix or a pumped flowing screed, which is priced by cubic metre and by pump setup. That setup charge is a fixed cost that does not scale with volume, and on small floors it dominates.

Insulation under the screed

Where the floor is over a void or the ground, insulation sits below the screed. Rigid boards are measured in square metres at the specified thickness, with 5 percent waste for cutting around penetrations.

Rigid insulation boards must be laid with staggered joints and tight together, and any gaps are thermal bridges. The material quantity for 60 m² is 63 m² of board, and the taping or foil sealing is a small but real line.

Underfloor heating, where it exists, sits between the insulation and the screed, and the screed thickness must increase to cover the pipe, typically to 65 mm or more. That change in thickness is a volume change and it is regularly forgotten when a heating system is added late.

Membranes and preparation

Preparation is the other half: sweeping, removing old adhesive, grinding high spots. On a renovation, that can be a full day for a two person gang on 60 m², and it is a labour line that no material order reveals.

Drying time, which is a programme cost

A sand and cement screed dries at roughly 1 mm per day for the first 25 mm and progressively slower after that. A 65 mm screed needs around two months before a moisture sensitive finish goes down, or a fast drying screed and a shorter wait.

That is not a material cost. It is a programme cost, and it decides when the finishes trade can start. On a tight programme, the choice of screed type is worth more than the difference in price per cubic metre, because a fast drying screed that allows flooring in two weeks can save a month of preliminaries.

Aluminium sulfate or calcium sulfate flowing screeds behave differently again and have their own drying and heating commissioning requirements.

Floor finishes: per square metre with a waste that depends on layout

Proprietary fast drying40 to 50 mm

|---|---|

FinishNotes on quantity
CarpetBy m², plus 10 percent, sold in widths that set the waste
Laminate or engineered timberBy m², plus 10 percent, plus underlay
Solid timberBy m², plus 10 to 15 percent, plus battens and clips
TileBy m², plus 10 percent, plus 15 percent for diagonal or small rooms
Vinyl sheetBy m², plus 15 percent, and joints welded

Carpet is the finish where roll width matters most. A 4 m wide carpet in a 3.4 m wide room wastes 0.6 m across the whole length, which is 15 percent of the roll. Two smaller rooms side by side can use that same width with no waste if the layout is planned, which is why a carpet takeoff should be done room by room with the roll width in mind.

A worked example

A ground floor of 60 m², replacing a suspended timber floor in a kitchen and a concrete floor in a hall.

That is a complete order for a floor that a rate per square metre would have priced as one line.

Skirting, trims and the junctions

Skirting is measured in linear metres of wall perimeter, less door openings, plus a mitre allowance. On a rectangular room, the perimeter is straightforward. On a room with a chimney breast, columns or a bay, measure each return.

The others that are counted or measured:

Productivity and the trades involved

Floors involve more trades than any other single element: groundwork, screeding, heating, flooring and decoration, and each one needs the previous one to be finished and dry.

Typical outputs, for planning rather than pricing: a screeding gang lays 100 to 150 m² of sand and cement screed a day, a flowing screed crew 200 to 300 m², a tiler 10 to 15 m² of floor tile, a timber floor fitter 25 to 40 m² of engineered board, a carpet fitter 40 to 60 m².

The programme point is that each of these is separated by a drying or curing period. Two floors that take three days of work can occupy six weeks of calendar time.

Stairs are a separate assembly

A staircase is not a floor, and it is priced on its own terms: treads, risers, strings, balustrade, spindles and handrail, plus the structural opening and the trimming joists around it.

For a new stair, count the steps and measure the balustrade. For a renovation, decide early whether the stair stays, is repaired or is replaced, because a repaired staircase that has to be protected through the whole job changes the access route for every trade after it.

Stair nosings and the finish to treads and risers are measured separately again, and on an open stair the underside is either plastered or left open, which is another decision with a price.

Common errors

  1. Pricing the finish and forgetting the screed
  2. Screed thickness not increased for underfloor heating pipe
  3. No flatness allowance, so levelling compound appears as a variation
  4. Carpet ordered by area without considering roll width
  5. Movement joints omitted in large tiled areas
  6. Drying time not in the programme, which delays every trade after it
  7. Skirting and thresholds missing from the order

Suspended timber floors and the repairs nobody budgets for

A suspended floor is measured by the area of deck, and priced as if the joists are sound. On a house older than fifty years, they often are not.

Two items appear once the boards come up. Rot at the joist ends where they sit in a wall, which needs splicing or a replacement section. And notching and drilling from years of plumbing and wiring, which has weakened joists that were marginal to begin with.

Neither is visible on a survey photograph and both are common. A renovation estimate for a ground floor should carry a repair allowance, stated as an allowance, so the client understands it is a provision rather than a guess hidden in the rate.

Level thresholds and the 15 mm problem

Accessibility requirements in most markets now limit the step at an external door, usually to something around 15 mm. That single requirement decides floor build up, because the finished internal floor cannot sit higher than the external paving plus the threshold limit.

The arithmetic runs backwards from the door. If the external level is fixed, the internal build up is fixed, and the insulation plus screed plus finish must fit inside it. That is why a 100 mm insulation specification sometimes becomes 60 mm of high performance board, and why the screed type changes.

Set this out before the insulation is ordered. A floor that meets the level threshold on paper and not on site is a door that will not open, and by then the screed is down.

Frequently asked questions

How thick should a screed be? 25 to 30 mm bonded, 50 mm unbonded, 65 to 75 mm floating over insulation, and deeper over underfloor heating.

How long before I can lay flooring on a screed? Roughly 1 mm per day for the first 25 mm, so about two months for a 65 mm traditional screed. Fast drying screeds cut that substantially.

How much waste on floor tiles? 10 percent for a straight layout in a square room, 15 to 20 percent for diagonal, small rooms or large format tiles.

Do I need underlay? For carpet, yes. For engineered timber, usually a combined underlay and vapour layer. For laminate, always.

How much skirting do I need? Room perimeter less door openings, plus 10 percent for mitres and waste.

Does the floor need to be level or flat? Both, and they are different properties. Level matters for furniture and doors, flat matters for the finish. Specify the tolerance before the screed is placed.

Do the layers in FRELUX

The FRELUX flooring calculator works from the sub floor up: membrane, insulation, screed volume by thickness, then finish, adhesive, underlay, skirting and trims, priced from your market's price book.

ResinBy m² at a specified thickness, and it is a specialist trade